22 November 2022
Glen Eira Multi-deck car parks (abandoned)
Council decided not to proceed with the proposed multi-deck commuter car park projects in Bentleigh and Elsternwick.
We are experiencing delays to our bundled branch collections (including the collection of Christmas trees) due to many bookings over the holiday period. If your scheduled collection has been impacted, please leave it on your nature strip and it will be collected as soon as possible. We appreciate your patience and apologise for any delays.
Enter text and select option from the drop-down list
Published on 05 December 2024
We are resurfacing Chesterville Road, Bentleigh East.
Status: on time
Timeline: works begin on Monday 9 December and will be completed by Wednesday 11 December, weather permitting.
Budget: $125K
As part of our 2024–25 Asphalt Resurfacing Works Program we are replacing the asphalt along Chesterville Road, Bentleigh East.
The works will take place in two stages. Day works between Bronson Road and Vasey Street will take place between 7am–5pm on Monday 9 December. Night works between Vasey Street and South Road will take place between 8pm Tuesday 10 December and 5am Wednesday 11 December.
There will be some changes to street access and on-street parking during the works. Please follow the signs to safely travel through the area.
We have appointed Prestige Civil Group to undertake the works.
22 November 2022
Council decided not to proceed with the proposed multi-deck commuter car park projects in Bentleigh and Elsternwick.
28 February 2023
We are committed to flood mitigation and continue to deliver a significant program of drainage improvement and stormwater detention across the municipality.
© 2025 Glen Eira City Council