Find out all the latest construction updates and site photos.
Construction updates
Works currently underway
- Northen carpark works including final asphalting
- External pavement areas and retaining walls
- Main switchboard, plant room, change room and pool hall fit-out
- Filling the pools
- Pool hall floor finishes
- Pool commissioning
- Landscaping
Works completed in the past month
- Carpark tree vaults
- Pool halls ceiling
- Plant slab waterproofing
- Installation of shade sails for the splash pad and outdoor 50m pool
- Dive pool tiling
Changes to on-site parking
An estimated 25 to 35 large construction vehicles will enter and exit the site each day. Efforts will be made to avoid peak traffic periods.
Civil works to the site carpark are still taking place and ADCO contractors will continue to park their vehicles off-site.
The estimated number of vehicles to park off-site is between 35–55 on weekdays and 20–30 on Saturdays. Contractors have been advised to park in the Koornang Park off street carpark adjacent to Koornang Oval, off Munro Avenue. On Saturdays, contractors will split parking requirements between the Koornang Oval off-street carpark and the southern side of Munro Avenue towards the Lord Reserve Pavilion, to allow parking for other users of the oval. This section of the street will also be used during the week if the Koornang Oval off-street carpark is full.
Contractors have been directed to avoid parking on Lyons Street and other side streets at all times.
Koornang Park
The eastern site fencing connecting to Koornang Park has been adjusted to allow the returning of soil back to the site. Works are ongoing, and once all soil is removed from Koornang Park, the grassed area will be reinstated.